Procedure for Approval of Major Capital Projects

Approval Date: 2016-12-06

Effective Date: 2016-12-06

Responsible Unit: Department of Facilities Management

Procedure

1. The Project Sponsor determines when a submission for approval of a Major Capital Project will be made and prepares the Formal Capital Project Approval Request and associated documentation. All Formal Major Capital Project Requests require approval of the Board of Regents before expenditures or preliminary design work can occur.

2. Formal Major Capital Project Approval Request submissions must include the following:

a. Project description;
b. Detailed justification for the project including proposed stakeholder management structure;
c. Identification of any special management/academic/operational issues;
d. Functional outline of the project including the space type, size, function, occupancy, and recommended acquisition method;
e. Confirmation from Campus Facilities Management that the University Space Standards and Guidelines have been considered and, where feasible, met;
f. Timing implications and required start-up schedules;
g. Defined funding source and financial plan including cash flow projections;
h. Detailed Major Capital Project Estimate prepared by Campus Facilities Management that includes the basis and assumptions under which the estimate has been prepared. Estimates must follow  the Detailed Major Capital Project Estimate Form.

3. Approval of a Formal Major Capital Project Approval Request requires the following sequence:

a. Review by PEC and approved by the President or designate; and
b. Review and approval by CPDC; and
c. Review and approval by the Board of Regents Finance Committee; and
d. Review and approval by the Board of Regents

4. The decision of the Board of Regents is:

a. Approval granted for the Vice-President (Administration, Finance, and Advancement) to proceed as proposed following the Procedure for Management of Major Capital Projects; or
b. Conditional approval, requiring the qualification or provision of additional data; or
c. Deferred for future consideration through the CPDC; or
d. Denied.

5. Board of Regents approval must include confirmation of the approved budget and preliminary construction schedule for each approved project.

6. In addition and in accordance with Sections 4.(2) and 37. of the Memorial University Act, approval of the Lieutenant-Governor in Council is required for certain projects, particularly those which incur liability or make expenditure for the purchase of lands or the erection of buildings.

 

Policies using this procedure:

Procedure Amendment History

There are past amendments for this policy:

Action: Created full working copy
Date: 2022-08-29 15:35:34
Action: REPLACED
Date: 2024-10-04 09:37:30
This procedure was replaced with a new version. Comment provided: Updated to reflect Vice-President titles as approved by the Board of Regents December 7, 2023
Action: Created full working copy
Date: 2024-10-07 13:23:19
Action: REPLACED
Date: 2024-10-07 13:23:39
This procedure was replaced with a new version. Comment provided: Updated to reflect Vice-President Council titles as approved by the Board of Regents December 7, 2023